How To Form A Prestressed Concrete Unit On A Prestressing Concrete Plant

How To Form A Prestressed Concrete Unit On A Prestressing Concrete Plant

Go through the following construction videos that show how to develop a prestressed concrete unit (Double T) on a prestressing concrete plant.

Double T is a multipurpose prestressing unit usually applied in parking structures but also be utilized in various buildings together with office buildings, industrial buildings, etc. The Double Ts contain the potentiality of supporting span extending to 60ft as well as up to 120ft.

Step 1 (Prestressed Concrete Unit Formation):

The initial step is to set up the necessary forms (here double T) as soon as the cleaning is completed. Under this construction video, a bed is arranged for 5 double T units having length 60ft long. Self stressing form is ideal for prestressing which can deal with prestressing compression force as well as the eccentricity of the strands.

Step 2:

The crew members can arrange strands in the form and transmit them through the prestressing plate. Strands are placed constantly over 5 units and later on segregated with the space provided by the dividers.

Step 3:

Strands already set in 2nd step are then tensioned to about 2 to 5 kips on the basis of gauge pressure reading. Here a mark is given on strands once the preload is applied. The strands are then tensioned and noted through gauge pressure on the hydraulic pump. Quality control Technician then verifies elongation of strands against theoretical elongation. It necessitates that force on gauge and elongation measured should be equal with a 5% tolerance limit. If it fails then strand should have been detained and then tensioned again.

Part One of how a double tee structural prestressed concrete member is plant produced.

Find out the final application below in this video and have a clear view of the entire procedure.

Enjoy the demonstration now 🙂

https://youtu.be/91fCagGP5Is

Video Courtesy: Precast Education Florida